Bucks New University
Summary
Installation of Data & Voice Cabling over 13 Floors
Location
High Wycombe
Systems
Excel Cat6
Start & Finish
Apr 2009 – Dec 2009
Project Description
Buckinghamshire New University’s camp has undergone an extensive £60m programme of rebuilding in 2009. A new, high-tech learning resources centre, known as the Gateway, forms the focal point of the University’s technology-led learning experience.
Able were contracted by BAM to install an 1,800 Excel Cat6 UTP cabling system, spread over the six patch rooms on the six floors of the new Gateway building extension. Able also installed an Blown Fibre (OM3) & a voice link backbone cabling infrastructure between each patch room and the main computer room on the 4th floor.