For further information call:

01442 219580

Veolia Three Valleys Water

Summary
Cabling of building

Location
Hatfield Business Park, Hatfield

Systems
Molex PowerCat 6 UTP Cat6

Start & Finish
Nov 2008 – Jan 2009

Project Description
Veolia Water (formally Three Valleys Water) consolidated their offices into the new HUB building in Hatfield, a building to house 750 office staff.

Able were contracted by Como to install a 3,000 outlet Cat6 data cabling system. Run over four floors, outlets were terminated in a grid of 8-way consolidation points installed under the false floor. Desk outlets were connected to the consolidation points through solid patch lead connections.

The project was completed over a period of two months.